How to Create and Use a Kanban Board

A kanban board shows your work as cards that move across columns. Learn how to set one up, pick WIP limits and track flow with real math.

Smiling team moving sticky notes across an office whiteboard
Photo: Pexels

A kanban board is a visual board that shows work as cards moving through columns, such as To Do, Doing and Done. Each card is one task, and its column shows where that task stands. Teams use kanban boards to see all their work at once, spot jams early and finish tasks faster.

To create a kanban board, list the real steps your work goes through, turn each step into a column, and put every task on a card. Then cap how many cards each column can hold, and pull new work only when a card leaves. For one team in one room, a whiteboard and sticky notes work best. For remote teams, a digital board wins.

The sections ahead explain the parts of a board and seven steps to build one. They also give a sample board, how to set work limits with basic math, a daily routine, the numbers to track, and the mistakes to avoid.

The Parts of a Kanban Board

Every kanban board has the same few parts. Once you know them, you can build a board for any kind of work.

  • Columns. Each column is one stage of your work. A basic board has To Do, Doing and Done, but most teams add more stages, such as Review or Waiting.
  • Cards. Each card is one piece of work. It holds a short title, an owner and often a due date.
  • WIP limits. WIP means work in progress. A WIP limit is the most cards a column may hold at one time, often written in the column title, such as “Doing (3)”.
  • Swimlanes. These are rows that split the board by type of work, client or person. They are optional.
  • Policies. These are short written rules, such as what “done” means for each column.
  • Commitment point. This is the spot where the team agrees to start a card. Before it, a card is only an idea.

The WIP limit is the part most people skip, and it is the part that makes the board work. Without it, a kanban board is only a to-do list with columns.

How to Create a Kanban Board in Seven Steps

Building a board takes about an hour for a small team. Then plan to adjust it in the first few weeks as you learn.

1. Map the Real Steps of Your Work

Write down what happens to a typical task from the moment someone asks for it until it is finished. For example, a blog post might go through Idea, Writing, Editing, Design, Scheduled and Published.

Use the steps your team really takes, not the ones it should take. If work often waits for a manager’s sign-off, that wait is a step too.

2. Turn Each Step Into a Column

Draw one column per step, from left to right. Then add a backlog column on the far left for work that has not started, and a Done column on the far right.

Keep the first version short. Five to seven columns is enough for most teams, because too many columns make cards hard to follow.

3. Split Columns Into Doing and Done Where Work Waits

Some stages have a hidden wait. For example, an edited post may sit for two days before design picks it up. So split that column into “Editing: in progress” and “Editing: done”. That way, the wait shows up on the board.

4. Write One Card for Each Task

Put each task on its own card. Keep tasks small enough to finish in a few days. Then add an owner and, if it matters, a due date or a client name.

Big tasks hide problems. So break a card such as “Launch new website” into smaller cards, such as “Write home page copy” and “Set up contact form”.

5. Set a WIP Limit for Each Active Column

Pick a limit for every column where work happens. A good first rule is the number of people who work in that column, plus one. So a column with two writers starts with a limit of three.

The backlog and Done columns get no limit. You will tune these numbers later, once the board has a few weeks of data.

6. Write the Board’s Rules

For each column, write one line on when a card may move on. For example, Editing is done when the editor has fixed spelling and checked every link. Post these rules on the board, so nobody argues about them later.

7. Pick a Time to Review the Board

Set a short daily check-in, about 15 minutes, in front of the board. Then add a longer weekly review to change columns or limits. Our weekly team meeting agenda template works well for that review.

Team planning work on a kanban board with sticky notes
Photo: Pexels

A Sample Kanban Board for a Marketing Team

The table shows a full board for a three-person content team. Each column has its own limit and rule.

ColumnWIP limitRule for moving a card on
BacklogNoneCard has a title, a goal and a target reader
Ready to write5Brief is approved by the team lead
Writing3Draft is complete with sources linked
Editing2Spelling fixed and all links checked
Design2Images and charts added and sized
Scheduled4Post is set in the CMS with a date
DoneNonePost is live and shared on social media

Notice that Editing and Design have the lowest limits. They each have one person, so a limit of two keeps each person on one task with one waiting. In contrast, Writing has three writers who share the load.

Read also: CBSE vs ICSE: How to Pick the Right Board

How to Set WIP Limits on a Kanban Board

WIP limits control how fast work moves. A rule called Little’s Law links three numbers:

Average cycle time = Work in progress ÷ Throughput

Cycle time is how long one card takes from start to Done. Throughput is how many cards the team finishes in a set time, such as a week.

Take a team with 12 cards in progress that finishes 8 cards a week. Its average cycle time is 12 ÷ 8, or 1.5 weeks. Now the team lowers its total WIP to 8 cards and still finishes 8 a week. As a result, the average cycle time drops to 1 week, a third faster, with no extra effort.

Total WIPCards finished per weekAverage cycle time
12 cards81.5 weeks
10 cards81.25 weeks
8 cards81 week

So lower limits finish work sooner, up to a point. If a limit is too low, people sit idle while they wait for work. Then raise that limit by one.

Watch the board for two signs. First, if a column is always full and the one after it is empty, the full column is the jam, so add help there. Second, if a column is often empty, its limit is too high upstream or its people need other work.

How to Use a Kanban Board Every Day

A board only helps if the team uses it every day. These habits keep cards moving.

  1. Read the board from right to left. In the daily check-in, start at Done and walk back. That way, the team talks about finishing work first.
  2. Pull, never push. Take a new card only when your column has room. Nobody drops work into a full column.
  3. Flag blocked cards. Mark any card that is stuck with a red dot or tag, and write why. Then the team agrees who will fix it.
  4. Finish before you start. If you have room for one card, help a teammate finish a stuck card before you pull new work.
  5. Keep the board current. Move your card the moment its status changes, so the board always shows the truth.

For personal work, the same board pairs well with planned focus time. Our time blocking guide covers how to book hours for the cards in your Doing column.

Kanban Board Numbers to Track

A board shows the present. However, a few numbers tell you if flow is getting better over the weeks.

  • Cycle time. Write the start date on each card and the finish date when it reaches Done. The gap in days is its cycle time.
  • Throughput. Count the cards that reached Done each week.
  • Work item age. For cards still in progress, count the days since they started. An old card is a warning before it becomes a late card.
  • WIP. Count the cards between the commitment point and Done each day.

Take ten finished cards with cycle times of 3, 4, 4, 5, 5, 6, 7, 8, 9 and 14 days. The average is 6.5 days. More usefully, 9 of the 10 cards finished in 9 days or less. So the team can tell clients that most requests finish within 9 days, and it can look hard at the 14-day card to learn what slowed it.

Physical vs Digital Kanban Boards

Both formats work, but they serve different teams.

Board typeWorks best forNot for
Whiteboard and sticky notesOne team in one room, short tasksRemote or hybrid teams
Digital board appRemote teams, file attachments, historyTeams that will not open the app daily
Spreadsheet boardA solo worker testing the ideaTeams with more than a few people

A whiteboard wins for a team that sits together. It is cheap, always in view, and moving a note by hand makes the daily check-in more active. However, it is not for remote teams, and it keeps no history unless someone photographs it.

A digital board app, such as Trello or Jira, wins for remote and hybrid teams. Cards can hold files, comments and dates, and the app keeps the history you need for cycle time. If you work alone, our list of Trello alternatives for freelancers compares other board apps.

When a Kanban Board Is the Wrong Tool

A kanban board shows flow but has no timeline. So a project with a fixed launch date and many tasks that depend on each other needs a timeline too. In that case, plan the dates in a Gantt chart and run the daily work on the board. Our guide on how to make a Gantt chart in Excel covers the timeline side.

A board also struggles with work that has no repeat steps, such as one big research question. In that case, a plain task list with weekly goals may serve better.

Read also: How to Create a Weekly Grocery Budget for a Family

Kanban Board Mistakes to Avoid

  • No WIP limits. The board fills up, and everything is half done.
  • Cards that are too big. A card that sits in Doing for a month hides every problem inside it.
  • Columns that match the org chart. Name columns after steps of work, such as Editing, so cards move by task instead of by team.
  • Stale boards. If cards move only before the meeting, the board stops being trusted.
  • Ignoring blocked cards. A flagged card needs an owner and a next step, or it stays stuck.
  • Too many columns. Twelve columns make the board hard to read and slow to update.

Questions About Kanban Boards

Is kanban the same as Scrum?

No. Scrum works in fixed sprints, with set roles and a goal for each sprint. Kanban has no sprints. Work flows one card at a time, and the team controls it with WIP limits.

Can I use a kanban board for personal tasks?

Yes. A personal board with To Do, Doing (limit 2) and Done works well. The low limit stops you from juggling too many tasks at once.

Who should own the kanban board?

One person, often the team lead, keeps the board tidy and runs the check-in. However, each person moves their own cards, so the board stays current without one person chasing updates.

What do the colors on kanban cards mean?

Whatever your team decides. A common setup uses one color per type of work, such as blue for client work and yellow for internal tasks, plus a red tag for blocked cards.

Joydeep Bhattacharya Avatar

Written by

Founder, Editor and Business Reporter, Bizolaunch

Free Tools for Founders

Calculators and templates built by Bizolaunch. Run the numbers in minutes.

Keep Reading